Ram|bunc|tious 24,564 1,944 July 12, 2012 at 10:29 AM
I'm using Visio 2010 with an expanded timeline where the displayed dates for the interval are not necessary. I can make them transparent to hide them, but then the description of the interval is below center and looks odd. Is there some setting I can set that disables display of the date range?

Sample image below, want to remove the date within the interval and center the text description:

1 Comments

1

Sign up for a Slickdeals account to remove this ad.

Joined Feb 2007
L10: Grand Master
7,354 Posts
2,746 Reputation
#2
The simplest method would be to edit the Document stencil Master. So:

1 - File/Shapes/Show Document Stencil

2 - In the Document Stencil right click on the Master you're after and
select Edit Master/Edit Master Shape

3 - The milestone is a 'Group' shape and has a setting to protect its
children so select the shape and click Show ShapeSheet from the Window menu

4 - Scroll down the ShapeSheet to the "Protection" section, find the
"LockGroup" cell and change its value to 0

5 - Now select the Date text shape (you may need to click twice as the first
click will only select the Group shape if its not selected already)

6 - With the Date shape selected, select "Protection..." from the Format
menu and uncheck the "From deletion" checkboxpress F2 and delete the
highlighted text

7 - Return to the group shape's ShapeSheet and change the "LockGroup" cell
back to 1. Close the ShapeSheet window.

8 - Close the Master edit window and accept the "Update shapes" message

9 - Right click the Master in the Document Stencil once more and select Edit
Master/MasterProperties...

10 - Check the "Match master by name on drop" checkbox

Note that this will be a permenant change for the respective document, so
you might want to test it on a copy first. As an alternative to deleting
the Date shape you might want to add a true/false type custom property
(Shape Data in 2007) to the page shapesheet, named something like "Show
milestone dates", that you could reference from the Date shape's Text Field
cell. Of course if this is the first time you've met the ShapeSheet then
you might be more comfortable with the above.
Reply Helpful Comment? 0 0
Page 1 of 1
1
Join the Conversation
Add a Comment
 
Copyright 1999 - 2016. Slickdeals, LLC. All Rights Reserved. Copyright / Infringement Policy  •  Privacy Policy  •  Terms of Service  •  Acceptable Use Policy (Rules)  •  Interest-Based Ads
Link Copied to Clipboard